Four Delhi-Katra expressway packages in J&K show up to 94 per cent progress

The Jakh-Vijaypur-Kunjwani stretch has recorded the highest physical progress among the four major packages in Jammu and Kashmir.

Four major packages of the Delhi-Amritsar-Katra Expressway Phase-II in Jammu and Kashmir have achieved physical progress between 66.74 per cent and 94.14 per cent, according to a Government of India document reported by Daily Excelsior.

The Jakh-Vijaypur-Kunjwani section, which includes spur connectivity to Jammu Airport, has recorded the highest progress at 94.14 per cent. This project, which began in September 2022, has a revised completion target of March 2027.

Package-XV, covering the stretch from Hiranagar Road to Jakh village, has reached 90.01 per cent progress. Its completion date has been revised to December 2026.

Package-XVIII, involving the Sidhra-Domel section of NH-44, has achieved 70.17 per cent physical progress with a revised completion target of June 2027. Package-XVII, covering the Kunjwani-Sidhra and Domel-Katra sections, has recorded 66.74 per cent progress and is targeted for completion by November 2027.

The four packages have a combined revised cost of Rs 10,109.24 crore, compared to an original estimate of Rs 8,457.14 crore. Cumulative expenditure on the projects so far stands at Rs 4,808.60 crore.