ACME Group begins execution of $3.6 billion green ammonia project in Odisha

The renewable energy company has made the final investment decision for the 760,000-tonne-per-annum facility in Paradip.

ACME Group has reached the final investment decision for its $3.6 billion green ammonia project in Odisha, moving the facility into the execution phase, according to reports by Business Standard, The Hindu and The Economic Times.

The plant, located in Paradip, is expected to be commissioned by 2029 and will have an annual production capacity of 760,000 tonnes. The facility will use renewable energy and electrolysers to produce green hydrogen, which will then be converted into ammonia via the Haber-Bosch process.

The project aims to reduce yearly greenhouse gas emissions by over 1.5 million tonnes. German engineering firm Thyssenkrupp Uhde has been appointed as the technology partner to design a 2,200-tonne-per-day ammonia synthesis loop.

ACME Group chairman Manoj Kumar Upadhyay said the decision is a critical milestone in moving from ambition to execution at scale. He noted the project would build on the company's experience in Duqm, Oman, to produce competitive molecules for various markets.

The company has secured long-term supply commitments, including 370,000 tonnes annually for Indian fertiliser companies through the Solar Energy Corporation of India (SECI) under the SIGHT scheme. Additionally, 83,000 tonnes per year will be supplied to Japan's IHI Corporation under the Long-Term Decarbonisation of Power Auction (LTDPA).

Brookfield has committed $600 million to ACME's green molecules business. Murzash Manekshana, head of asset management in India, energy, at Brookfield, said this investment would help deliver more than 1.5 million tonnes per annum of green molecule projects.