Maharashtra summons Adani officials over Tarali project cost estimates

The forest department halted work on the 1,500 MW project after it failed to obtain wildlife clearance.

Maharashtra Forest Minister Ganesh Naik summoned representatives of the Adani Group for a meeting on Tuesday at Mantralaya. The meeting followed a stop-work order issued by the forest department on November 13 for the 1,500 MW Tarali Pumped Storage Project in Satara district, which lacked approval from the National Board for Wildlife (NBWL).

According to reports from Telegraph India and Hindustan Times, the scrutiny involves two different cost estimates for the project: Rs 5,675 crore and Rs 56.75 crore. The difference is significant because the required conservation payment depends on the project cost used for calculation. Officials noted that reducing the estimate from Rs 5,675 crore to Rs 56.75 crore would lower the deposit from Rs 227 crore to Rs 2.27 crore.

Adani Green Energy Ltd (AGEL) denied allegations that it sought to lower costs to diminish statutory obligations. The company stated that the Rs 56.75 crore figure related solely to site investigations and survey costs, while the SBWL considered the total project cost to be Rs 5,675 crore.

Principal Chief Conservator of Forests (Wildlife) M Srinivas Reddy said the department has not accepted the revised estimate and has asked the company to provide an explanation and supporting documents. The Union Ministry of Environment, Forest and Climate Change (MoEF&CC) directed the state forest department on November 6 to investigate the matter on priority.