Texas settlement allows 88-acre data centre near Westlake homes
Developer PowerHouse will pay nearly $1.9 million to resolve a lawsuit from residents concerned about noise and environmental impacts.
A settlement has been reached to allow an 88-acre data centre project to proceed near Westlake, Texas, following legal challenges from local homeowners. According to the Times of India, the agreement between developer PowerHouse, the City of Keller, and affected residents includes nearly $1.9 million in payments and new operational protections.
The facility, located near the northeast corner of U.S. 377 and Westport Parkway, will consist of four buildings covering approximately 1.1 million square feet. Residents of the Lakes of Marshall Ridge neighbourhood had filed a lawsuit, citing concerns over noise, traffic, drainage, and environmental disruption due to the site's proximity to their backyards.
Under the terms signed on November 5, PowerHouse must pay $1.5 million for a noise mitigation fund, $300,000 for fire protection, and $76,000 for the legal and consulting costs of Keller within 45 days. The settlement also mandates that noise levels stay below 56 decibels during the day and 49 decibels during the overnight period from 7 p.m. to 7 a.m.
Additional requirements include increasing the height of a protective berm from 8 feet to 10 feet and extending sound monitoring to three years. Diesel generator testing is restricted to the hours between 10 a.m. and 4 p.m., and backup generators must meet EPA Tier 4 emissions standards.
Westlake Mayor Kim Greaves stated the centre would generate about $5 million annually for the town during its first 10 years, increasing town revenue by approximately 14 per cent. The Town of Westlake noted that revenue is expected to reach about $7 million annually after the first decade.
The Westlake Town Council approved the development agreement on November 12, providing a path forward for the project.