Tamil Nadu seeks long-term power deals to manage summer demand
The state utility is pursuing five-year agreements to address projected electricity deficits expected to rise during the upcoming summer months.
The Tamil Nadu government is looking to secure long-term power to meet electricity needs during an extended summer influenced by the El Nino effect, according to The New Indian Express.
The Tamil Nadu Power Distribution Corporation Limited (TNPDCL) is attempting to procure 3,000 MW through new five-year power purchase agreements starting from March 2027.
A senior official from TNPDCL stated that the utility previously floated four short-term procurement tenders, but these were cancelled because of high tariffs and insufficient responses from generators.
In a fifth tender, companies quoted rates between Rs 9 and Rs 20 per unit, but the required quantity of power was not secured, the official said.
A senior official noted that the evening peak power deficit is projected to grow from 1,388 MW in January to 5,544 MW in April, with further deficits of 3,987 MW in May and 4,796 MW in June.
The official said these projected shortages are a concern because they may impact electricity availability for the agricultural sector, industries, and domestic consumers during peak summer.
TNPDCL is currently receiving 2,830 MW through long-term agreements with 11 generation companies, though agreements for 2,122 MW are set to expire in September 2028.