India's first bullet train service to launch in late 2027
The Surat to Vapi section will be the first part of the high-speed rail corridor to open, according to Railway Minister Ashwini Vaishnaw.
India's inaugural high-speed rail service is scheduled to begin operations in the last quarter of 2027, starting with the Surat to Vapi section, according to a Rediff report. Railway Minister Ashwini Vaishnaw confirmed the timeline and stated that the full corridor to Mumbai will open in subsequent phases.
Vaishnaw noted that as of September, construction includes 456 km of pier work and 371 km of viaduct construction. He added that six lakh noise barriers have been placed along a 299 km stretch and 9,300 OHE masts have been installed across a 206 km viaduct.
The project includes India's first undersea rail tunnel, a 7 km stretch located beneath Thane Creek in Maharashtra. Two Tunnel Boring Machines, which were launched in July 2026, are being used for the 21 km Maharashtra tunnel, of which 5 km has already been excavated.
Regarding rolling stock, ICF and BEML are manufacturing indigenous B28 trainsets designed for 280 kmph. The first body frame is complete and undergoing testing, with track trials expected by mid-2027. A faster B35 model designed for 350 kmph is planned for the future.
Addressing previous delays, Vaishnaw said the project faced a two-and-a-half-year delay in Maharashtra due to land acquisition and state permissions, plus a two-year delay caused by COVID. He stated that serious construction only began in earnest in 2021.