MPCB issues stop-work notice for Adani Green project in Satara

Key points card: MPCB directed Adani Renewable Energy One Ltd to halt work; Excavation and construction occurred without necessary permissions in Satara; The project has an estimated investment of Rs 5,675 crore.
Key points from the story. As reported by Times Now, Indian Express, Hindustan Times.

The Maharashtra Pollution Control Board directed Adani Renewable Energy One Ltd to halt unauthorised excavation and construction in Sawarghar village.

The Maharashtra Pollution Control Board (MPCB) issued a stop-work notice on Friday, November 20, to Adani Renewable Energy One Ltd regarding activities in Sawarghar village, Satara district. According to reports from The Indian Express and Hindustan Times, the notice concerns excavation and construction at two land parcels for a temporary labour camp and storage areas.

The MPCB regional officer in Pune, Kiran Hasabnis, directed the company to immediately cease all ongoing and proposed work at the sites. The board stated the work was being conducted without necessary permissions or intimation to the MPCB and without obtaining environmental clearance from the competent authority.

This follows a November 13 order from the Maharashtra Forest Department, which halted construction at the 1,500 MW Tarali Pumped Storage Project due to a lack of National Board for Wildlife approval. The project has an estimated investment of Rs 5,675 crore.

An Adani Green Energy spokesperson said the activities at the specific land parcels were for short-term construction support and are not part of the permanent project infrastructure. The spokesperson added that permanent components have the required clearances and that the company is submitting a response to the MPCB, noting that activities at those sites have been suspended in the interim.

The notice was issued after Satara honorary wildlife warden Rohan Bhate filed a complaint seeking an inquiry into the construction. A forest department official stated that no construction is currently underway and a report will be submitted to the Ministry of Environment, Forest and Climate Change next week.