Waste litters Marina Beach cycle track as opening date remains uncertain
The 2.3km track is more than 90 per cent complete, but officials have not provided a deadline for its opening.
The under-construction 2.3km cycle track along Marina Beach in Chennai is littered with cow dung, food waste and tyre marks, according to The Times of India. The track stretches from near the Lighthouse signal to Madras University.
The Chennai Metropolitan Development Authority (CMDA) laid the track as part of the ₹18.45-crore Marina Heritage Corridor project. This project includes lighting, gardens, viewing decks and pedestrian amenities.
CMDA member secretary Rahul Nadh said more than 90 per cent of the work is complete and the project remains on track. He stated that the CMDA is in the process of handing the stretch over to the Greater Chennai Corporation (GCC).
While the GCC approved the work in August 2025, the project was initially scheduled to open in January. Officials said in September that work had stopped due to a lack of funds.
GCC commissioner G S Sameeran said his agency will take over only after the CMDA hands over the stretch. Nadh said a mutual agreement to handover will be taken soon, but provided no deadline for the handover or reopening.