All U-girders launched on Koyambedu-Alandur stretch of Chennai Metro phase II project
The 14.5 km corridor is expected to open next year as track work reaches advanced stages.
Chennai Metro Rail Limited has completed the launching of all U-girders on the 14.5 km Koyambedu-Alandur stretch of its phase II project, according to The Hindu.
The last U-girder was launched on Sunday between Butt Road and Kathipara Junction over Paul Wells Road using two high-capacity hydraulic cranes.
The completed stretch consists of 911 U-girders with lengths between 15 metres and 33.33 metres, and an average weight of approximately 135 tonnes.
A press release said that erecting works used various methodologies, including launching girders and high-capacity hydraulic cranes, based on site conditions.
Construction at locations such as Kaliamman Koil Street, Butt Road, and Paul Wells Road faced challenges including space constraints and underground or overhead utility lines.
The press release also noted that the integrated flyover along Mount-Poonamallee Road added complexity to the girder launching operations.
The final girder at Paul Wells Road was difficult to erect due to a space crunch, requiring one crane to be positioned within a nearby church premises and another in a narrow street.
The stretch is expected to be opened next year.