Bengaluru Metro Blue Line trial runs begin with 2027 opening target

Key fact card: 2027 year the target year for the corridor to open for public use, Karnataka, 25 November 2026.
2027 year the target year for the corridor to open for public use. As reported by The New Indian Express, India Today, The Hindu.

The 19-km Phase 2A corridor is expected to open by mid-2027 to provide transport relief along the Outer Ring Road.

Trial runs for the Bengaluru Metro Blue Line Phase 2A section commenced on Tuesday, covering the first four stations from KR Puram towards Mahadevapura, according to The New Indian Express.

Greater Bengaluru Development Minister Krishna Byre Gowda inspected the trial run at Doddanekkundi Metro Station. He stated that the 19-km corridor, which includes 13 stations, is targeted to open for public use by mid-2027.

The minister said testing will continue this month and cover four more stations next month. The installation of the automatic signalling system is expected to be completed by January, with the mandatory safety certification process starting after February.

The entire 58.2-km Blue Line, connecting Central Silk Board to Kempegowda International Airport via KR Puram and Hebbal, is being implemented at an estimated cost of Rs 20,000 crore. The government aims to complete the full corridor within the next 18 months.

Gowda noted that the corridor will serve the Outer Ring Road, where approximately 12 lakh people work. He also addressed financial challenges, stating that foreign exchange fluctuations have increased the loan repayment burden by nearly 30 per cent.

Regarding Metro finances, the minister said BMRCL records an annual loss of around Rs 700 crore when including depreciation. He clarified that no decision has been taken on increasing Metro fares.