Pallivasal Extension Scheme cost reaches ₹632.59 crore after delays

The 60-MW hydropower project took over 20 years to complete, according to Kerala State Electricity Board documents.

The 60-MW Pallivasal Extension Scheme has reached a total cost of ₹632.59 crore, according to documents from the Kerala State Electricity Board (KSEB), The Hindu reported. The hydroelectric project, which adds 60 MW of capacity to the state power grid, was inaugurated by Chief Minister Pinarayi Vijayan in March 2026.

The project originally received administrative sanction in 2001 for ₹175.86 crore. In 2006, the work was assigned to the ESSAR-DEC-CPPL Consortium for ₹268.01 crore, but that contract was terminated in 2018 following technical and contractual issues. The remaining works were subsequently carried out through various separate packages.

Following a direction from the Kerala State Electricity Regulatory Commission, the KSEB issued a formal revised administrative sanction for ₹632.59 crore in a November 24, 2026 order. The KSEB noted that the total cost includes interest, finance charges, employee costs, and administrative expenses.

The KSEB board of full-time directors examined the causes of the delay in October 2026. The board has decided to conduct an independent study through a committee or an external expert agency to recommend improvements for project management practices.

Regarding accountability, the KSEB management decided in February 2026 not to take action against officials for the delays. This decision followed a report from the KSEB Vigilance wing, which stated that while lapses caused delays, there was no evidence of malicious intent or vested interest by the officials.