Mumbai commission orders builder to pay Rs 83.56 lakh to flat buyers
The Mumbai Suburban consumer commission ruled that financial issues cannot justify prolonged delays in delivering possession of a Mulund West flat.
A Mumbai Suburban consumer commission has directed M/s Riddhi Sidhi Corporation and its partners, Parveen Chamaria and Chetan Bhanushali, to pay approximately Rs 83.56 lakh to three flat buyers. According to a report by The Times of India, the order follows the developer's failure to deliver a 313.45 sq ft flat in Mulund West on time.
The complainants, Mohan Anarse, Akash Anarse and Sunita Anarse, booked the 19th-floor unit in the Excellente project on February 14, 2019, for Rs 69.14 lakh. Possession was due by July 31, 2020, but the commission noted that construction had stopped with only 50% to 60% completed when the complaint was filed.
The commission ordered a refund of Rs 52.80 lakh with 9% simple interest per annum from July 31, 2020. It also awarded Rs 75,000 for mental agony and financial hardship, and Rs 25,000 for litigation costs. The commission stated that the complainants could not be expected to wait indefinitely for a project with no certainty regarding delivery.
The buyers had booked the flat under a subvention scheme where EMIs were meant to start after possession, but they began paying them in August 2020 due to the delay. The commission rejected the developer's implied defence that funding issues caused the delay, stating financial insufficiency cannot justify such delays.
The builder and partners must comply with the order within 45 days. Following payment and adjustments with the housing finance institution, the parties must coordinate to release any mortgage and register a deed cancelling the original sale agreement.