Road ministry tightens bidding norms for government-funded projects
The ministry has linked contractor bidding capacity to performance ratings and project delays to improve construction quality and execution.
The road transport ministry has updated bidding and contract conditions for fully government-funded or Engineering, Procurement and Construction (EPC) projects, according to the Times of India.
The new rules link a contractor's bidding capacity to their performance ratings and delays in ongoing projects. This replaces the previous method of assessing the best-performing financial year.
The modifications to the Request for Proposal (RFP) aim to prevent contractors with poor execution records from taking on more work than they can handle. The ministry has also reduced the maximum number of members in joint ventures (JVs) from three to two.
Under the revised framework, JVs will generally only be allowed for projects costing more than Rs 1,000 crore. Technical eligibility conditions for specialised infrastructure, such as tunnels and major bridges, have also been strengthened.
The ministry has rationalised non-performance criteria from 20 to seven and linked performance security to contractor ratings, with requirements ranging from 3% to 5% of the bid price. If the lowest bidder is ineligible, the authority can now annul the process and invite fresh bids.
To increase transparency, bidders must disclose details regarding ongoing litigation, arbitration, disputes, and penal actions, and keep this information updated during the bidding process.