Pending 8-km stretch delays Mumbai-Goa highway completion

Cost overruns for the Maharashtra section of the NH-66 project have exceeded Rs 2,000 crore as work continues on five delayed packages.

An investigation by The Indian Express shows that approximately 8 km of work remains pending on the Maharashtra section of the 592-km Mumbai-Goa highway. The delays involve five specific packages, including two bypasses, a 192-metre bridge, a 1.8-km flyover, and hill cutting at four locations. The cost for the final stretch is estimated to have increased by over Rs 2,000 crore.

The overall cost estimate for the Maharashtra section has risen by about 44 per cent, from Rs 12,532 crore to more than Rs 18,100 crore. Ministry of Road Transport and Highways (MoRTH) officials attributed this increase to land acquisition, changes in work scope due to site constraints, and the construction of additional underpasses requested by local residents.

Union Minister of Road Transport and Highways Nitin Gadkari expressed regret regarding the delays during the opening of a corridor in Goa on September 9. He indicated he would not attend the expected inauguration of the highway next year.

V Umashankar, Secretary of MoRTH, stated that 99 per cent of the highway is now complete and all remaining work should be finished by April next year. Officials noted that delays in Maharashtra have been caused by land acquisition issues, local protests, and cash flow or loan default problems.

The project, originally conceived in 2006 to upgrade NH-66, has seen multiple deadline revisions. While the 120-km Goa section is complete, the pending work in Maharashtra is required to link the two state capitals.