Adani Energy Solutions wins Bihar transmission project

The project aims to evacuate 2,400 MW of power from the upcoming Pirpainti thermal power plant by late 2028.
Adani Energy Solutions Ltd (AESL) has secured a transmission project in Bihar to evacuate 2,400 MW of electricity from the upcoming Pirpainti ultra-supercritical thermal power plant, according to reports by BusinessLine, Business Today and Financial Express.
The project, titled ‘Evacuation of Power from 3X800 MW STPP Pirpainti’, was awarded through the tariff-based competitive bidding (TBCB) route. It will be executed via a special purpose vehicle (SPV) named Vikramshila Power Transmission Ltd.
Once commissioned, the scheme is expected to produce an annual tariff of approximately Rs 500 crore. AESL aims to complete the work by the fourth quarter of 2028.
The infrastructure work includes building four gas-insulated substations (GIS) at Jhanjharpur, Bethauli and Begusarai. It also involves installing 400 kV and 220 kV double-circuit transmission lines and managing line-in-line-out (LILO) arrangements for existing 220 kV and 132 kV lines at Jhanjharpur.
Adani Energy Solutions CEO Kandarp Patel said the scheme will create a robust evacuation system and strengthen the transmission backbone in Bihar to help meet growing power demand. He added that the infrastructure would improve grid resilience and support long-term energy security.
The project will increase the company's transmission network by 881 circuit kilometres and 3,160 MVA of transformation capacity. Following this, AESL's total transmission capital expenditure pipeline will reach approximately Rs 91,500 crore.