Adani Energy Solutions wins 2,400 MW power transmission project in Bihar

Key fact card: 2,400 MW power to be evacuated from Pirpainti thermal power plant, Bihar, 19 November 2026.
2,400 MW power to be evacuated from Pirpainti thermal power plant. As reported by Business Today, BusinessLine, The Tribune.

The project is expected to generate an annual tariff revenue of approximately Rs 500 crore once it is commissioned.

Adani Energy Solutions Limited (AESL) has secured a project to evacuate 2,400 MW of electricity from the upcoming Pirpainti thermal power plant in Bihar, according to Business Today and BusinessLine.

The project, titled ‘Evacuation of Power from 3X800 MW STPP Pirpainti’, was awarded through the Tariff-Based Competitive Bidding (TBCB) route. It will be executed via a special purpose vehicle, Vikramshila Power Transmission Ltd.

The scheme involves building four Gas Insulated Substations at Jhanjharpur, Bethauli, and Begusarai. It also includes developing 400 kV and 220 kV transmission lines and upgrading existing infrastructure to improve grid reliability in the state.

AESL CEO Kandarp Patel said the scheme would create a strong system to move 2,400 MW of power and bolster Bihar's transmission network. He noted that the infrastructure would help the state meet rising electricity needs and support national energy security.

Upon completion, which is targeted for the fourth quarter of 2028, the project will add 881 circuit kilometres of lines and 3,160 MVA of transformation capacity to the company's portfolio. This will bring AESL's total transmission network to 30,683 ckm.

With this latest win, the transmission capital expenditure pipeline for AESL has increased to approximately Rs 91,500 crore.