Adani Energy Solutions wins Bihar power transmission project

Key fact card: 2,400 MW electricity to be evacuated from Pirpainti thermal power plant, Bihar, 22 November 2026.
2,400 MW electricity to be evacuated from Pirpainti thermal power plant. As reported by The Pioneer, Business Today, The Tribune.

The project aims to evacuate 2,400 MW of electricity from the upcoming Pirpainti thermal power plant.

Adani Energy Solutions Limited (AESL) has secured a contract to transport 2,400 MW of electricity from the upcoming Pirpainti Ultra Super Critical Thermal Power Plant in Bihar, according to The Pioneer and The Tribune.

The project, titled “Evacuation of Power from 3X800 MW STPP Pirpainti”, was awarded through the Tariff Based Competitive Bidding (TBCB) mechanism. It will be executed via a Special Purpose Vehicle (SPV) named Vikramshila Power Transmission Ltd and is expected to be finished by the last quarter of 2028.

Once operational, the scheme is projected to generate an annual tariff of approximately Rs 500 crore. The infrastructure will include 881 circuit kilometres of transmission lines and 3,160 MVA of transformation capacity, bringing the company's total network to 30,683 ckm and 146,585 MVA.

The work involves building four Gas Insulated Substations at Jhanjharpur, Bethauli, and Begusarai. It also includes 400 kV double-circuit lines connecting Pirpainti, Jhanjharpur, Begusarai, and Bakhtiyarpur, alongside 220 kV lines and upgrades to existing infrastructure.

Kandarp Patel, CEO of Adani Energy Solutions, said the scheme would create a strong evacuation system for the 2,400 MW capacity and reinforce the state's transmission backbone. He added that the project would improve grid resilience and assist Bihar in meeting rising power needs.

Following this win, the transmission capital expenditure portfolio of AESL stands at roughly Rs 91,500 crore.