Goa commission orders fabricator to refund man for unsafe mobile home

Key fact card: Rs 2.4 lakh refund Pune-based firm must refund to a Goa resident, Goa, 27 November 2026.
Rs 2.4 lakh refund Pune-based firm must refund to a Goa resident. As reported by Times of India, Financial Express.

A Pune-based firm must refund Rs 2.4 lakh plus compensation to a resident for delivering a rusted and incomplete structure.

The North Goa District Consumer Disputes Redressal Commission has directed a Pune-based fabricator to refund Rs 2.4 lakh to a Goa resident, Kuriakose, for delivering an incomplete and unsafe mobile home. According to reports by The Indian Express and Financial Express, the commission also ordered the firm to pay Rs 10,000 in compensation for mental agony and harassment.

Kuriakose had commissioned the customised mobile home on wheels to accommodate caregivers at his house in Carambolim, Goa, while he recovered from surgery. He found the fabricator through a Facebook advertisement and was promised delivery within four weeks. He made three payments totalling Rs 2.4 lakh between February 20 and May 3, 2025.

The complainant alleged that the delivered structure differed substantially from the approved design, citing poor workmanship and rusting on both the interior and exterior. An architect engaged by the fabricator's office inspected the structure on July 2, 2025, and reported serious construction defects and safety risks. The architect stated the construction occurred without her supervision or approval.

The commission noted that the fabricator was served notice but failed to appear or file a response, leading the matter to proceed ex parte. In its November 3 order, the commission, led by president Bela N Naik and member Auroliano de Oliveira, ruled that the firm's failure amounted to a deficiency in service.

The order mandates the refund of the Rs 2.4 lakh with 7 per cent interest per annum. If the amount is not paid after the appeal period, it will attract interest at 3 per cent per annum until final payment.