Adani Energy Solutions wins Bihar transmission project to evacuate 2,400 MW power
Our main story on this: Adani Energy Solutions wins Bihar power transmission project
The project is expected to generate an annual tariff of approximately Rs 500 crore once it is commissioned by late 2028.
Adani Energy Solutions Limited (AESL) has secured a transmission project in Bihar to evacuate 2,400 MW of power from the upcoming Pirpainti Ultra Super Critical Thermal Power Plant, according to The Pioneer. The project was awarded through the Tariff Based Competitive Bidding (TBCB) mechanism.
The initiative, titled “Evacuation of Power from 3X800 MW STPP Pirpainti”, will be carried out via a Special Purpose Vehicle (SPV) named Vikramshila Power Transmission Ltd. It is scheduled for completion by the last quarter of 2028.
The work involves building four Gas Insulated Substations (GIS) at Begusarai, Bethauli, and Jhanjharpur. The network will feature 400 kV double-circuit lines linking Pirpainti to Jhanjharpur and Begusarai, and Begusarai to Bakhtiyarpur, alongside 220 kV lines for the Jhanjharpur-Bethauli and Begusarai-Begusarai Town connections.
Adani Energy Solutions CEO Kandarp Patel said the scheme would establish a robust evacuation system for the 2,400 MW capacity while strengthening the transmission backbone of Bihar. He added that the project would help the state meet rising power demand and improve grid resilience.
Once finished, the project will add 881 circuit kilometres of lines and 3,160 MVA of transformation capacity to the AESL portfolio. This will bring the company's total network to 30,683 ckm and 146,585 MVA, with a transmission capital expenditure pipeline of approximately Rs 91,500 crore.